We design, permit, and build accessory dwelling units in Fullerton and North Orange County — detached ADUs, attached ADUs, junior ADUs, and garage conversions. Every ADU starts with a feasibility review of your lot, so you know what fits and roughly what it costs before you commit to full design.
What can you build on a single-family lot?
California law requires cities to allow ADUs on most single-family lots, and in many cases a combination of units: an ADU created within existing space such as a garage, a junior ADU inside the house, and a new detached ADU (Government Code §66323). What actually fits on your lot depends on lot size and shape, setbacks, existing structures, utility capacity, and — in Fullerton's Residential Preservation Zones — the City's design guidelines.
Four types of ADU
Garage conversion
Turns an existing garage into a living unit. Usually the lowest-cost path when the structure is sound, but older garages often need foundation, framing, insulation, and utility upgrades to meet current code.
Detached ADU
A new, separate building in the backyard. The most privacy and the most design freedom; also the highest cost, and it must include solar under the Energy Code unless an exception applies.
Attached ADU
A new unit built onto the main house with its own entrance. Treated as an addition for energy-code purposes.
Junior ADU (JADU)
A smaller unit created within the walls of the existing house, such as a converted bedroom suite. Under state law, cities must require JADUs to be rented for terms longer than 30 days.
How long does an ADU permit take?
For a lot with an existing house, California law requires the city to approve or deny a complete ADU application within 60 days (Government Code §66317), and to tell you within 15 business days whether the application is complete. The clock starts only when the application is complete, and correction rounds add time — which is why clear, coordinated drawings matter as much as the design itself.
Why one firm for design and construction
ADUs are small buildings with tight budgets. When the architect and the builder are the same licensed firm, the design is priced as it's drawn, field questions are answered on site, and there is one party responsible from feasibility to final inspection. If you'd rather bid the permit set to other contractors, you can.
Deciding between an ADU, an addition, or a remodel? Read Remodel, add on, or build an ADU?